|
|
|
|
|
|
|
|
Transportation Engineering:
|
|
|
|
|
|
|
|
|
Prefabricated Pedestrian WEI has designed pedestrian bridges having conventional, spread, slab, and pile foundations. Design focus has been on ease and speed of installation, cost, stability and function, lack of disruption to the surrounding area, and beauty.
Pre-Cast WEI has also designed for pre-cast vehicular bridges, including an arterial bridge with a 22' span where utility relocates, excavation, placement, backfill, and readiness for operation had to occur over a 3 day weekend, and the road was open by Monday evening!
Field Constructed WEI also provides full service in designing larger field cast and fabricated bridges. Site work design is handled by WEI including; utility locates, relocates, and coordination; traffic routing, detouring, and bypasses; hydrology and hydraulic evaluations; approach design; grading and drainage; and permitting and coordination. WEI subcontracts support services including: surveying; potholing; geotechnical exploration; and the bridge structure design which, actually, is not the major work involved in a bridge design project, but rather the site work provided by WEI.
|
|
|
|
|
|
|
|
|
Mill Creek Flood Control Parkway Project (Phase 2, 4, & 5), Moab, UT Metric design and construction oversight of concrete bike & pedestrian paths, jetties, channel improvements, creek crossing, arterial underpass, crossing under UDOT bridges, and permitting. Project also included design of minor arterial road widening. The underpass was 22' wide and 9' high, and doubled as a pedestrian underpass and overflow flood control structure. As noted above, the particular challenge was to perform all utility relocates, excavation of the roadway, plaacement of the foundation, 3-sided pre-cast bridge structures, and have everything completed and ready for opening traffic in 3 days -- and it was. Good planning, tight specifications, and fortunately a good contractor brought it all together.
Mill Creek Flood Control & Parkway Project Phase III, Moab, UT Design concrete bike/pedestrian paths, riverside improvements, pedestrian bridge abutments and permitting.
|
|
|
|
|
D-1/2 Road Pathway Project, Mesa County, CO As part of 2 mile 8' wide pathway project, designed roadside pedestrian bridge.
Scott M. Mattheson Wetlands Project, Moab, UT Bridge hydraulics & abutment design and associated permitting. Client was very particular about not disrupting the environment. Design approach was to have narrow crane back up to creek on path, drive piles, repeat on the opposite side, unload pre-fabricated bridge, and carefully swing and weave it around and through branches and set. And it worked -- not a single branch was scarred.
Cannon Site Access, Moab, UT Evaluated hydraulics in Mill Creek and designed bridge abutments.
Mill Creek Project Phase I, Moab, UT Design of concrete bike/pedestrian paths and two bridges.
|
|
|
|
|
|
|
|
|